First Caisson Has Been Successfully Submerged In Nador Port Project

First Caisson Has Been Successfully Submerged In Nador Port Project

In Nador Port Project, which is constructed in Morocco; the first caisson has been successfully submerged. Following the installation of the superstructure (steel grids and generators) and pumps to the C3A caisson (dimensions 21,30 m x 28,30 m x 25,70 m) with a weight of 8.300 tons, it was transported to the Barge by using 50 Nos of hydraulic jacks each 250 t capacity.

3.150 m3 concrete and 702 t rebar were used in the said caisson.

We would like to congratulate our colleagues for this great achievement and wish them continuous success.