<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>STFA SOIL Group Archives - STFA Group</title>
	<atom:link href="https://www.stfa.com/en/tag/stfa-soil-group/feed/" rel="self" type="application/rss+xml" />
	<link>https://www.stfa.com/en/tag/stfa-soil-group/</link>
	<description>We Know How</description>
	<lastBuildDate>Thu, 27 Feb 2020 06:44:20 +0000</lastBuildDate>
	<language>en-GB</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	
	<item>
		<title>STFA SOIL Group</title>
		<link>https://www.stfa.com/en/stfa-soil-group/</link>
		
		<dc:creator><![CDATA[stfaconst]]></dc:creator>
		<pubDate>Thu, 21 Oct 2004 15:14:03 +0000</pubDate>
				<category><![CDATA[News]]></category>
		<category><![CDATA[Sohar Refinery Project]]></category>
		<category><![CDATA[Sohar Refinery Project in Oman]]></category>
		<category><![CDATA[STFA SOIL Group]]></category>
		<guid isPermaLink="false">http://stfa.com/?p=359</guid>

					<description><![CDATA[<p>STFA SOIL GROUP has succesfully completed two of his contracts in Oman. Piling Works of the Offsite Area, Sohar Refinery Project ...</p>
<p>The post <a href="https://www.stfa.com/en/stfa-soil-group/">STFA SOIL Group</a> appeared first on <a href="https://www.stfa.com/en">STFA Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><strong>STFA SOIL GROUP has succesfully completed two of his contracts in Oman.</strong></p>
<p>Piling Works of the Offsite Area, Sohar Refinery Project in Oman&#8221; was completed on 30.08.2004.The agreement was made on 19 January 2004 with Dodsal Co. LLC. The project consisted of 2134 nos cast in situ bored piles with outer diameters varying from 450 mm to 600 mm with a total length of 21805 m. The Piling Works Related to Sohar Refinery Project Sohar, Oman&#8221;, were completed on 19 August 2004. The agreement was made on 27. December 2003 with CCC Oman L.L.C. The scope of the project covered 5796 nos of cast in situ bored piles with outer diameters varying from 450 mm to 900 mm with a total length of 54497 m.</p>
<p>The post <a href="https://www.stfa.com/en/stfa-soil-group/">STFA SOIL Group</a> appeared first on <a href="https://www.stfa.com/en">STFA Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
	</channel>
</rss>
