STFA Marine Construction Company has started to mobilize for the Arzew Oil Port Breakwater Repair Project in Algeria.

STFA Marine Construction Company has started to mobilize for the Arzew Oil Port Breakwater Repair Project in Algeria. The project will be carried out by STFA-Cosider-Meditram Groupment with a total budget of 10 Million USD. The project is financed by the Ministry of Public Works of Algeria and Directory of Public Works of Oran. STFA’s scope of work in the Groupment will cover the placement of 80.000 tons of stone material, 720 numbers and 40 tons of tetrapod precast concrete members and 3332 numbers of 4.16 m3 of cubes. The duration of the project will be 12 months.